WHAT SHOULD I BE DOING INSTEAD OF THIS?
 
December 1st, 2013 By German Lopez | News | Posted In: News, City Council, Mayor, Streetcar

CAF USA Warns of Streetcar Cancellation Costs

Letter comes on eve of council vote on streetcar project

streetcarRendering: CAF USA / City of Cincinnati

The company in charge of building Cincinnati's streetcars says the city would incur substantial costs if it cancels the streetcar project after it's already gone through some construction and design work.

The Nov. 30 letter from CAF USA Vice President Virginia Verdeja to former Mayor Mark Mallory arrived just one day before Mayor John Cranley, who opposes the streetcar project, and an anti-streetcar majority were sworn in.

"CAF will have to recover all the incurred expenses as well as all the additional cost of cancelling the contract, which would be substantial too," Verdeja writes in the letter.

The letter explains that, on top of the sunk expenses on design work, cancellation would require CAF to pull back on various established deals with subcontractors, which would spur further costs.

For streetcar supporters, the letter renews fears of litigation that could crop up if the project were canceled and contractors decided to pursue their full payday.

Those legal costs would fall on the already-strained operating budget that pays for day-to-day services like police and firefighters instead of the capital budget that finances big capital projects like the streetcar, according to city spokesperson Meg Olberding.

The letter was first posted on the Cincinnati Streetcar Facebook page. Its validity was confirmed in an email to CityBeat from former Mallory staffer Jason Barron.

On Nov. 21, Streetcar Project Executive John Deatrick warned the costs of canceling the $132.8 million streetcar project could nearly reach the costs of completion after accounting for $32.8 million in estimated sunk costs through November, a potential range of $30.6-$47.6 million in close-out costs and up to $44.9 million in federal grant money that would be lost if the project were terminated.

Earlier on Sunday, hundreds of streetcar supporters rallied in Washington Park and walked the planned streetcar route in support of the project. They're threatening a referendum if the new City Council moves to pause or cancel the project.

City Council plans to vote on pausing the project on Monday. Because of threats from the federal government that a mere delay could lead to the loss of federal grants, streetcar supporters claim a pause would equate to cancellation.

Read the full letter below:

Updated at 6:13 p.m. with the PDF of the letter.

 
 
 
 