June 24th, 2013 By German Lopez | News | Posted In: News, Budget, Streetcar

Streetcar Project to Move Forward

Council measures increase capital funding, require more transparency

streetcar

The streetcar project remains on track following today's votes by City Council's Budget and Finance Committee, which approved increased capital funding and accountability measures that aim to keep the public informed on the project's progress.

The increased funding was previously proposed by City Manager Milton Dohoney to fix a $17.4 million budget gap. The money will come from more issued debt and pulled funding from various capital projects, including infrastructure improvements around the Horseshoe Casino. Under state law, none of the capital funding could be used for operating budget expenses, such as police and fire.

The accountability measures also require the city administration to report to City Council on the streetcar's progress with a timeline of key milestones, performance measures, an operating plan, staffing assessments and monthly progress reports.

"The progress reports should be easy-to-understand and made available online to ensure transparency and accountability to City Council and to citizens," the motion reads.

Council members Roxanne Qualls, Laure Quinlivan, Chris Seelbach, Yvette Simpson and Wendell Young voted for the measures. Council members P.G. Sittenfeld, Chris Smitherman and Charlie Winburn voted against both. Councilwoman Pam Thomas voted against the funding ordinance, but she abstained from voting on the motion imposing accountability measures.

Qualls, who revealed the accountability measures in a press conference prior to today's committee meeting, said the measures will move the streetcar forward and help keep the public informed.

"I will vote today to continue the streetcar project because we need to continue moving Cincinnati forward," she said. "At the same time, while I remain a supporter, it is with the recognition that it is time for a reboot on the project to instill public confidence in its management."

Smitherman did not seem convinced.

"I believe the administration will be back asking for more money on the streetcar," he claimed, pointing to pending litigation with Duke Energy over who is legally obligated to pay for moving utility lines to accommodate the project.

Smitherman and Sittenfeld also criticized their colleagues for not bringing the accountability measures to a vote earlier in the process.

"You would think seven years ago there would have been a motion like this in front of us," Smitherman said, referencing when City Council first approved the streetcar project.

Among the accountability motion's items is an operating plan, which streetcar critics have long demanded.


The city administration estimates operating the streetcar will cost about $3.5 million a year, indicating in the past that casino tax revenue would be used to pay for the costs.

Supporters say those costs will be outweighed by the city's estimated three-to-one return on investment for the streetcar project — an estimate backed by studies from advising company HDR and the University of Cincinnati.

Simpson in particular argued the costs will be made up through increased revenue as the streetcar brings in more businesses and residents to Cincinnati.

Still, Simpson says those estimates don't matter to streetcar opponents.

"If it was $5, there would be individuals who don't support this project," she said.

Winburn responded by saying he supports the streetcar as a concept, which roused laughter from streetcar supporters in the audience. Throughout the project's many hearings, opponents of the streetcar have often said they support streetcars as a concept — at least until they have to put their support to a vote or commit funding.

Still, Winburn added, "Even if you all are wrong, I want to commend you for fighting for what you believe in."

The streetcar project's $17.4 million budget gap is a result of construction bids coming in $26 million to $43 million over budget — a result of "errors in bid documents," according to Qualls.

Besides increasing funding, the city is also hiring John Deatrick, project manager of The Banks, to head the streetcar project. Multiple city officials, including Qualls and Quinlivan, have praised Deatrick for his ability to bring down project costs and put large projects on track.

The funding currently set for the streetcar will only go to the first phase of the project. The final plan calls for tracks stretching from The Banks to the Cincinnati Zoo.

"If the intent of the streetcar would only be to go from The Banks to just north of Findlay Market, then I never would have said it's a project worth doing," Dohoney previously told City Council. "The intention has always been to connect the two major employment centers of the city and go beyond that."

But Smitherman says talk of another phase is financially irresponsible: "I want to indicate to the public that they (the city administration) don't have a budget for the second leg."

The funding ordinance and accountability motion must now be approved by a full session of City Council, which has the same voting make-up as the Budget and Finance Committee.

If it's approved, the federal government has committed another $5 million to the streetcar that will help restore certain aspects of the project previously cut because of budget concerns.

 
 
06.24.2013 at 06:27 Reply

I would personally like to thank all the commuting suburbanites who helped make this day possible. By coming into the city to work you have helped us subsidize a project you can not vote for, approved by city leaders you cannot vote out, all because you would rather live in the depths of hell (cookie cutter cul-de-sac) than inside the city limits. Thank you for paying your 2.1%, we very much appreciate it.

 

06.26.2013 at 01:29 Reply

Really Thad? Really? You are celebrating something  that is costing the city millions of dollars that has essentially already failed? There have been 3 murders, THREE, in close proximity to the proposed line in the last couple weeks. This plan is a waste of time and a bad idea. Take this money and put it into education and maybe we can go somewhere as a city. 

 

 

 
 
Close
Close
Close